| Home | Search | Pollutants | About the Database |

| Incident # | No LDEQ Number Available |
| State Police # | No Information Given |
| Incident Date | 2011-03-21 |
| Report Date | 2011-03-22 |
| Follow-up Date | 0000-00-00 |
| Follow-up: | No |
| Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
| Sludge | No Information Given | WWTP Wasted Sludge Digester Tank | NO | NO | NO | BRQ |
According to the refinery letter, "a pinhole leak developed about 6 feet up on the side of our WWTP Wasted Sludge Digester Tank."
BRQ: The pinhole leak was repaired and the WWTP operator was instructed to not raise the tank level above the pinhole as a precaution. The tank will be replaced in the next 2-3 months. Until then "normal daily control tests and compliance tests will continue." Refinery letter only. No LDEQ or SPOC reports.
Connect With Us: